Saturday, February 29, 2020

An Analysis of Project Networks as Resource Planning Tools

| Following is an analysis of project networks as resource planning tools. The analysis will be segmented into three topical areas to include: * Risks associated with leveling resources, compressing, or crashing projects, and imposed durations or â€Å"catch-up† as the project is being implemented; * Advantages and disadvantages for reducing project scope to accelerate a project and what can be done to reduce the disadvantages * Three options for reducing project duration and advantages and disadvantages to these options Risks Associated with Leveling Resources, Compressing, or Crashing Projects, and Imposed Durations or â€Å"Catch-Up† The text (Gray and Larson, 2008) gives good definitions for the risks associated with certain actions used to offset resource constraints. The act or process of evening out â€Å"resource demand by delaying noncritical activities (using slack) to lower peak demand† (Gray and Larson, 2008) is considered leveling resources. This action ultimately increases the resource utilization, which is more than likely the desired result. Even though one may get the desired results resource-wise, leveling resources often results in pushing out the end-date of a project. In most cases, that is the extreme outcome. Another risk that bears its head when slack is reduced, is loss of flexibility which equates to an increase in critical activities. Without slack anywhere in a project network, ALL activities become critical. This means that everything has to fall perfectly in place in order to stay on the prescribed timeline. Compressing a schedule means that you will be conducting project activities in parallel. Compressing is not applicable to all project activities. A good example can be seen if you have activities labeled â€Å"Hire Workers† and â€Å"Dig Foundation†. You can’t implement the â€Å"Hire Workers† and â€Å"Dig Foundation† activities in parallel because to dig a foundation you need to have someone to do the digging. (brighthub. com/office/project-management/articles/51684. aspx#ixzz0ongX7ECF, 20 May 2010). Risks of compressing include: * Increases risk of rework * Increases communications challenges, and may * Require more resources Crashing a schedule involves allocating more resources so that an activity can be completed on time or before time, assuming that by deploying more resources the activity can be completed earlier. One good aspect about crashing a schedule (just like compressing), you do not need to crash all activities. The activities that impact the schedule are those with no slack, thus being the only ones that are affected. Risks associated with this action are as follows: â€Å"Budget: Since you allocated more resources, you will not deliver the project on-budget. Demoralization: Existing resources may get demoralized by the increase in people to complete activities that were originally assigned to them. Coordination: More resources translates to an increase in communication challenges† (brighthub. com/office/project-management/articles/51684. aspx#ixzz0onfuKUmj, 20 May 2010). These risks combined or by themselves can ultimately pose the overall risk of reducing the effectiveness of the existing resources. Advantages and Disadvantages for Reducing Project Scope to Accelerate a Project and what can be Done to Reduce the Disadvantages Reducing the scope of the project can lead to big savings both in time and costs. It typically means the elimination of certain tasks. At the same time scaling down the scope may reduce the value of the project such that it is no longer worthwhile or fails to meet critical success factors. An advantage to reducing project scope is the project is more likely to stay on schedule and on budget. It also allows for more focus being applied to the remaining deliverables in the project scope. A disadvantage that may arise is loss of quality in work due to key quality deliverables selected to be cut in order to balance the timeline of the project. The key to offsetting the disadvantages is â€Å"reassessing the project requirements to determine which are essential and which are optional. This requires the active involvement of all key stakeholders. More intense re-examination of requirements may actually improve the value of the project by getting it done more quickly and for a lower cost. † (just answer. com 21 May 2010) Three Options for Reducing Project Duration and Advantages and Disadvantages to these Options Reducing the duration a project can be managed by reducing the duration of an activity/activities almost always results in higher direct cost. When the duration of a critical activity is reduced, the project’s critical path can be change with other activities and that new path will determine the new project completion date. Following are three options to reducing project duration. Adding Resources: This is a popular method to reduce project time by assigning additional staff and equipment to activities-if it is assessed appropriately. The activities at hand need to be researched accordingly and proper determinations of how much time will be saved prior to just throwing bodies at it. The first thing that comes to mind when you add resources is â€Å"double the resources, reduce the length of the project in half. The unforeseen disadvantage that arises is the increase in the amount of time that an existing team member must spend in explaining what has been done already and what is planned. This increases the overall communication time spent by the team which phenomenally ends up adding/losing valuable time. Outsourcing Project work: A common method for shortening the project time is to subcontract an activity. The subcontract may have access to superior technology or expertise that will accelerate the completion of the activity (Gray and Larson, 2008). Additionally, significant cost reduction, and flexibility can be gained when a company outsources (Gray and Larson, 2008). Disadvantages that may be experienced are conflict due to contrasting interpersonal interactions and internal morale issues if the work has normally been done in-house (Gray and Larson, 2008). Scheduling Overtime: The easiest way to add more labor to a project is not to add more people, but to schedule overtime. The www. businesslink. gov outlines potential advantages of using overtime working include: * a more flexible workforce * the ability to deal with bottlenecks, busy periods, cover of absences and  staff shortages without the need to recruit extra staff * increased earning for employees * avoidance of disruption to jobs where the workload is more difficult to share,  e. g. ransport and driving * the ability to carry out  repair and maintenance which has to be done outside normal working hours However, disadvantages may include: * the expense of premium overtime rates * inefficiency if employees slacken their pace of work in order to qualify for overtime * regular long wo rking hours, which  can adversely affect employees’ work, health and home lives * fatigue, which  may increase absence levels and lead to unsafe working practices * employee expectations of overtime, leading to resentment and inflexibility if you try to withdraw it. (businesslink. gov, 22 May 2010) Conclusion Usage and availability of resources are essential considerations when establishing Project Networks in Resource Planning. This analysis has focused on some of the risks of certain actions used to offset resource constraints, advantages/disadvantages for reducing project scope, and options/advantages/disadvantages for reducing project duration. If implemented correctly, careful consideration of the outlined risks will make managing a project a little less painless. References Brighthub. com. Difference Between Schedule Crashing and Compressing, Retrieved 20 May, 2010 http://www. brighthub. com/office/project-management/articles/51684. aspx#ixzz0onfuKUmj Brighthub. com. When to Crash or Compress a Schedule, Retrieved 20 May 2010 http://www. brighthub. com/office/project-management/articles/51684. aspx#ixzz0onfuKUmj Read also: Conveyor Belt Project An Analysis of Project Networks as Resource Planning Tools | Following is an analysis of project networks as resource planning tools. The analysis will be segmented into three topical areas to include: * Risks associated with leveling resources, compressing, or crashing projects, and imposed durations or â€Å"catch-up† as the project is being implemented; * Advantages and disadvantages for reducing project scope to accelerate a project and what can be done to reduce the disadvantages * Three options for reducing project duration and advantages and disadvantages to these options Risks Associated with Leveling Resources, Compressing, or Crashing Projects, and Imposed Durations or â€Å"Catch-Up† The text (Gray and Larson, 2008) gives good definitions for the risks associated with certain actions used to offset resource constraints. The act or process of evening out â€Å"resource demand by delaying noncritical activities (using slack) to lower peak demand† (Gray and Larson, 2008) is considered leveling resources. This action ultimately increases the resource utilization, which is more than likely the desired result. Even though one may get the desired results resource-wise, leveling resources often results in pushing out the end-date of a project. In most cases, that is the extreme outcome. Another risk that bears its head when slack is reduced, is loss of flexibility which equates to an increase in critical activities. Without slack anywhere in a project network, ALL activities become critical. This means that everything has to fall perfectly in place in order to stay on the prescribed timeline. Compressing a schedule means that you will be conducting project activities in parallel. Compressing is not applicable to all project activities. A good example can be seen if you have activities labeled â€Å"Hire Workers† and â€Å"Dig Foundation†. You can’t implement the â€Å"Hire Workers† and â€Å"Dig Foundation† activities in parallel because to dig a foundation you need to have someone to do the digging. (brighthub. com/office/project-management/articles/51684. aspx#ixzz0ongX7ECF, 20 May 2010). Risks of compressing include: * Increases risk of rework * Increases communications challenges, and may * Require more resources Crashing a schedule involves allocating more resources so that an activity can be completed on time or before time, assuming that by deploying more resources the activity can be completed earlier. One good aspect about crashing a schedule (just like compressing), you do not need to crash all activities. The activities that impact the schedule are those with no slack, thus being the only ones that are affected. Risks associated with this action are as follows: â€Å"Budget: Since you allocated more resources, you will not deliver the project on-budget. Demoralization: Existing resources may get demoralized by the increase in people to complete activities that were originally assigned to them. Coordination: More resources translates to an increase in communication challenges† (brighthub. com/office/project-management/articles/51684. aspx#ixzz0onfuKUmj, 20 May 2010). These risks combined or by themselves can ultimately pose the overall risk of reducing the effectiveness of the existing resources. Advantages and Disadvantages for Reducing Project Scope to Accelerate a Project and what can be Done to Reduce the Disadvantages Reducing the scope of the project can lead to big savings both in time and costs. It typically means the elimination of certain tasks. At the same time scaling down the scope may reduce the value of the project such that it is no longer worthwhile or fails to meet critical success factors. An advantage to reducing project scope is the project is more likely to stay on schedule and on budget. It also allows for more focus being applied to the remaining deliverables in the project scope. A disadvantage that may arise is loss of quality in work due to key quality deliverables selected to be cut in order to balance the timeline of the project. The key to offsetting the disadvantages is â€Å"reassessing the project requirements to determine which are essential and which are optional. This requires the active involvement of all key stakeholders. More intense re-examination of requirements may actually improve the value of the project by getting it done more quickly and for a lower cost. † (just answer. com 21 May 2010) Three Options for Reducing Project Duration and Advantages and Disadvantages to these Options Reducing the duration a project can be managed by reducing the duration of an activity/activities almost always results in higher direct cost. When the duration of a critical activity is reduced, the project’s critical path can be change with other activities and that new path will determine the new project completion date. Following are three options to reducing project duration. Adding Resources: This is a popular method to reduce project time by assigning additional staff and equipment to activities-if it is assessed appropriately. The activities at hand need to be researched accordingly and proper determinations of how much time will be saved prior to just throwing bodies at it. The first thing that comes to mind when you add resources is â€Å"double the resources, reduce the length of the project in half. The unforeseen disadvantage that arises is the increase in the amount of time that an existing team member must spend in explaining what has been done already and what is planned. This increases the overall communication time spent by the team which phenomenally ends up adding/losing valuable time. Outsourcing Project work: A common method for shortening the project time is to subcontract an activity. The subcontract may have access to superior technology or expertise that will accelerate the completion of the activity (Gray and Larson, 2008). Additionally, significant cost reduction, and flexibility can be gained when a company outsources (Gray and Larson, 2008). Disadvantages that may be experienced are conflict due to contrasting interpersonal interactions and internal morale issues if the work has normally been done in-house (Gray and Larson, 2008). Scheduling Overtime: The easiest way to add more labor to a project is not to add more people, but to schedule overtime. The www. businesslink. gov outlines potential advantages of using overtime working include: * a more flexible workforce * the ability to deal with bottlenecks, busy periods, cover of absences and  staff shortages without the need to recruit extra staff * increased earning for employees * avoidance of disruption to jobs where the workload is more difficult to share,  e. g. ransport and driving * the ability to carry out  repair and maintenance which has to be done outside normal working hours However, disadvantages may include: * the expense of premium overtime rates * inefficiency if employees slacken their pace of work in order to qualify for overtime * regular long wo rking hours, which  can adversely affect employees’ work, health and home lives * fatigue, which  may increase absence levels and lead to unsafe working practices * employee expectations of overtime, leading to resentment and inflexibility if you try to withdraw it. (businesslink. gov, 22 May 2010) Conclusion Usage and availability of resources are essential considerations when establishing Project Networks in Resource Planning. This analysis has focused on some of the risks of certain actions used to offset resource constraints, advantages/disadvantages for reducing project scope, and options/advantages/disadvantages for reducing project duration. If implemented correctly, careful consideration of the outlined risks will make managing a project a little less painless. References Brighthub. com. Difference Between Schedule Crashing and Compressing, Retrieved 20 May, 2010 http://www. brighthub. com/office/project-management/articles/51684. aspx#ixzz0onfuKUmj Brighthub. com. When to Crash or Compress a Schedule, Retrieved 20 May 2010 http://www. brighthub. com/office/project-management/articles/51684. aspx#ixzz0onfuKUmj Read also: Conveyor Belt Project

Thursday, February 13, 2020

Eroding Privacy Rights Essay Example | Topics and Well Written Essays - 1500 words

Eroding Privacy Rights - Essay Example   A watershed moment in world history, the morning of September 11th, 2001 will forever be ingrained in the American national psyche. From a political, social and economic perspective, the hijackings of 9/11 were unparalleled in scope and sheer devastation. In a fascinating article entitled "Measuring the Effects of the September 11 Attack on New York City†, it was estimated that the direct cost of the attack stood at between $33 billion and $36 billion to the city of New York (Bram, Orr & Rappaport 55). In addition to the direct economic costs associated with terrorism and the threat of further terrorism, 9/11 also had important political ramifications.   The USA Patriot Act of 2001 (a contrived acronym meaning Uniting and Strengthening America by Providing Appropriate Tools Required to Intercept and Obstruct Terrorism) was established in the aftermath of September 11th to protect Americans from the threat of future terror on American soil.   Controversial from the outse t, the Patriot Act represented a serious departure from established legal norms and prior American jurisprudence with respect to privacy legislation (ACLU 2008).   Created under the pretense of securing the United States against the threat of terror in the wake of 9/11, the Patriot Act of 2001 significantly strengthened the scope of powers afforded to law enforcement agencies while redefining the term terrorism to include domestic terror, i.e. homegrown terror perpetrated by American citizens.

Saturday, February 1, 2020

Public formulation and implementation Essay Example | Topics and Well Written Essays - 500 words

Public formulation and implementation - Essay Example Public formulation is concerned with the generation of ideas that can help the public sector achieve a certain set of strategy. This process calls for expressions of interests from the experts. Experts from professional background such as; economists and researchers are always called upon to help the public administrators evaluate on any possible investment opportunity. After a lengthy evaluation of various strategies, the public administrator picks one project. Before doing so, a cost-benefit analysis is done to weigh on the investment viability. This is usually done to evaluate on the project that has high returns and less costs. The life years of the project is also taken into consideration. The longer the life year of the project determines the chance of investing on the project. Project approval is the second strategic steps that a public administrator follows. After the cost-benefit analysis of the project is done, internal rate of return (IRR) is also done. IRR analysis is done in order to examine the returns that the investment will realize in the entire life years of the project. The public administrator then approves for the most viable project. They approve the project and prepare the budget. Once the budget is approved, the project then prepares for the next step; implementation process. Implementation of this project is then executed. A public administrator deploys quality personal into performing this task. Day-to-day monitoring of this project is done to ensure that all the steps and processes are followed to the later. The chief project manager keep a record of the implementation process to make sure that all the provided steps is adhered to strictly. Implementation process is the key to the viability of the project as this will determine whether the project will be realized or not. An independent project expert that the public administrator appoints should work to